WSLC Construction Update
The building is beginning to take shape! Precast walls are mostly up on the Worship Center portion of the building. The foundation and footing work has been slowed by the rain and will continue into the next couple of weeks. We are expecting steel to arrive on site November 16 and are looking forward to our Beam Signing Celebration on Wednesday, December 2. Hope you can join us!
Previous Updates
Beginning October 8, our campus construction team will be working to connect utilities for the new Worship and Student Life Center. This phase of the project is expected to take about a week and will involve trenching in the area between Main, SPBI, and the stadium. At the same time, foundation work continues in preparation for the precast walls.